Status Reports: where are we now!

November 1st: Still waiting for WE Energies to hook up our 480 3 phase electrical, applied for 13 months ago, they have gotten our power to the pole across the street. Now they just need to get it across the street and connected to our new service, which was installed some time ago.

October 30th: new column foundations were poured inside the building, which will enable us to use the 2nd floor as a venue space. It was previously built just for storage, so it required 132 new joists to be installed in between all the older joists, new girders, and new columns. Each joist required about 1 hour labor to install.

September 30th: New electrical service panels were installed.

Windows are all replaced on west side! This is probably the first time in over half a century the interior has seen sunshine! Windows on alley side will be last exterior renovations.

On February 28th, Littleport received a conditional use permit to operate a brewery in Downtown Racine.

On March 1st, Littleport was approved for a loan from the City of Racine to finance brewing equipment needed for this business.

On March 20th, the City of Racine Common Council confirmed the March 1st committee approval of our loan package. Soon we will order our equipment!

Although most of our equipment is being acquired from local suppliers, Just say no to tariffs on imports, almost all microbreweries will be affected by this issue.

Read our most recent newspaper article here: Journal Times article
http://journaltimes.com/business/local/new-downtown-craft-brewery-financed/article_cebae497-3158-5c38-b3b8-68e53a975e49.html